Scheduled power outage on Dec. 30
There will be a scheduled power interruption on Saturday, Dec. 30, from 7:30am to 12:30pm to allow Commonwealth Utilities Corp. line crew to safely replace three wooden power poles with concrete poles along Chalan Tun Thomas P. Sablan in San Antonio.
This is part of an ongoing Hazard Mitigation Project that involves replacing 787 wood poles with concrete poles. A total of 325 wood poles have already been replaced. The remaining 462 wood poles will be scheduled for replacement at a later time.
Areas to be affected include the Kiya 2 line of Chalan Tun Thomas P. Sablan in Chalan Piao (Sherwood, Hopwood Middle School, Subway, Mobil Chalan Piao, Gold Ribbon, and Da Bao), Atuhong P1., Alupyang Pl., Juan Nong St., Hamalap Ln., and San Isidro Av.
The A-4 wastewater lift station will be affected but not water wells. The Chalan Piao traffic light will be affected.
Because of the scale of work that will be performed, CUC asks travelers to take alternate routes or to exercise caution when driving through the affected areas.
For more information, contact the CUC Customer Call Center (664-4282) or monitor our Facebook page for the latest updates. (CUC)