Load Shedding Schedule
Friday, August 26, 2005
10am – 12 noon Lateral under Feeder 3 – Affected are areas around East West Rental in Chalan Laulau (if necessary).
3pm – 5pm Kiya 4 – 2nd Partial – Areas affected are Susupe (including Saipan Community School) and portions of Chalan Kanoa Districts 2, 3 and 4 (including Sister Remedio School)
5pm – 7pm Feeder 4 – 2nd and 3rd Partials – Areas affected are portions of Capitol Hill, Mt. Tapochao, Talofofo, Agag, As Teo, Papago, Kagman area (including schools) and Kagman I, II, III
7pm – 9pm Kiya 2 – 2nd Partial – Areas affected are Chalan Kanoa District 3 (including WSR Elementary School), and portions of Districts 1 and 2, Tun Doi Road, Fina Sisu, portions of As Perdido, Chalan Piao and San Antonio
Three of the eight generators at Saipan’s primary power plant are under repair. If the weather remains cool and if customers can be part of the solution by using only one household air conditioner or a fan and conserve all other energy, the Commonwealth Utilities Corp. will do everything in its power to keep electricity on for all of the eight electrical grids or feeders. However, if the temperature rises and customers turn on more air conditioners, this will force CUC into a weekend load shedding schedule as follows:
Saturday, August 27, 2005
10am – 12 noon Kiya 1 – 3rd Partial – Areas affected are CPA Airport, Koblerville (including Koblerville Elementary, Saipan Southern High School and Koblerville Subdivision), As Perdido, As Gonno and portions of Afetnas
12 noon – 2pm Feeder 4 – 2nd and 3rd Partials – Areas affected are portions of Capitol Hill, Mt. Tapochao, Talofofo, Agag, As Teo, Papago, Kagman area (including schools) and Kagman I, II, III
2pm – 4pm Feeder 3 – 2nd Partial – Areas affected are Gualo Rai, Chalan Laulau, portions of China Town and As Falipe
4pm – 6pm Feeder 2 – 2nd Partial – Areas affected are Garapan Beach Road (including Kristo Rai Church) and Chalan Laulau (Beach Road)
6pm – 8pm Kiya 4 – 2nd Partial – Areas affected are Susupe (including Saipan Community School) and portions of Chalan Kanoa Districts 2, 3 and 4 (including Sister Remedio School)
8pm – 10pm Feeder 3 – 2nd Partial – Areas affected are Gualo Rai, Chalan Laulau, portions of China Town and As Falipe
Sunday, August 28, 2005
9am – 11am Kiya 2 – 2nd Partial – Areas affected are Chalan Kanoa District 3 (including WSR Elementary School), and portions of Districts 1 and 2, Tun Doi Road, Fina Sisu, portions of As Perdido, Chalan Piao and San Antonio
11am – 1pm Feeder 2 – 2nd Partial – Areas affected are Garapan Beach Road (including Kristo Rai Church) and Chalan Laulau (Beach Road)
1pm – 3pm Kiya 4 – 2nd Partial – Areas affected are Susupe (including Saipan Community School) and portions of Chalan Kanoa Districts 2, 3 and 4 (including Sister Remedio School)
3pm – 5pm Feeder 3 – 2nd Partial – Areas affected are Gualo Rai, Chalan Laulau, portions of China Town and As Falipe
5pm – 7pm Feeder 4 – 2nd and 3rd Partials – Areas affected are portions of Capitol Hill, Mt. Tapochao, Talofofo, Agag, As Teo, Papago, Kagman area (including schools) and Kagman I, II, III
7pm – 9pm Kiya 1 – 3rd Partial – Areas affected are CPA Airport, Koblerville (including Koblerville Elementary, Saipan Southern High School and Koblerville Subdivision), As Perdido, As Gonno and portions of Afetnas