CUC load shedding schedule

By
|
Posted on Jul 24 2008
Share

The Commonwealth Utilities Corp. would like to inform the public that as the rehabilitation and maintenance repairs continue on the engines and generators at the Power Plant 1, the load shedding schedule for July 26 through August 1, 2008, will be as follows:

[B]8am – 10am Feeder-2: Second Partial[/B]

Fishing Base south to San Jose Intersection

[B]10am – 12pm Kiya-4: Second Partial [/B]

Susupe, Mount Carmel south to portions of Chalan Kanoa and Chalan Kiya Village

[B]12pm – 2pm Feeder-4: Second Partial[/B]

Capitol Hill, As Teo, Kagman and portions of Papago

[B]2pm – 4pm Feeder-1: Second & Third Partial[/B]

99 Cents Store and portions of Garapan and Upper Navy Hill, Annaks Condominiums

[B]4pm – 6pm Feeder-7: Entire Grid[/B]

Lower Base industrial area, north to Tanapag, Achugao, San Roque, As Matuis and Marpi.

[B]6pm – 8pm Kiya-1: First Partial[/B]

Kannat Tabla, Botanical Garden, San Vicente, Dandan, Airport Road, Isley Field, Lower Dandan

[B]8pm – 10pm Kiya-2: Second Partial [/B]

Koblerville, As Gonno, San Antonio and Afetnas

The first partial in each of the respective feeder/kiya could be included to the schedule should the second partial be insufficient. Water and wastewater services will also be affected in the respective areas as a result of the power outages. CUC will make all efforts to keep to this schedule but may be modified in future public notices. This schedule may also be altered to address particular emergencies when necessary. [B](CUC)[/B]

Disclaimer: Comments are moderated. They will not appear immediately or even on the same day. Comments should be related to the topic. Off-topic comments would be deleted. Profanities are not allowed. Comments that are potentially libelous, inflammatory, or slanderous would be deleted.